CONSTRUCTIONAMENDED

Jefferson City City Council Regular Meeting Agenda Packet 2026-06-01

Wastewater Contract Amended for Additional Sewer Rehab

$154,156.00 (Change Order 1); new total $1,443,506.00City of JeffersonMORGAN CONTRACTING INCJune 1, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Jefferson City’s wastewater improvement contract with Morgan Contracting, Inc. was amended by Change Order 1, adding $154,156.00 for additional trenchless sewer repairs and manhole rehabilitation. The change increases the total contract to $1,443,506.00 and extends the completion deadline by 135 days.

Contract Details

Contract Amount

$154,156.00 (Change Order 1); new total $1,443,506.00

Vendor

MORGAN CONTRACTING INC

Agency

City of Jefferson, TN

Contract Type

CONSTRUCTION

Document Date

June 1, 2026

Contract Term

Contract time extended by 135 days to 255 days for substantial completion and 285 days for final payment

Renewal Info

Change Order 1 increases the contract amount and extends substantial completion to 255 days and final payment to 285 days from the original start; prior change orders are listed as N/A.