Southwest School Fence Project Change Order Approved

$50,783.36 (original cost $310,905.00, new total $361,688.36)Roosevelt School DistrictCHASSE BUILDING TEAMJanuary 6, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

CHASSE Building Team received board approval for a change order at Southwest School, adding $50,783.36 to cover revised fencing design for increased campus security. Total project cost is now $361,688.36, with completion targeted for March 2026.

Contract Details

Contract Amount

$50,783.36 (original cost $310,905.00, new total $361,688.36)

Vendor

CHASSE BUILDING TEAM

Agency

Roosevelt School District, WA

Contract Type

CONSTRUCTION

Document Date

January 6, 2026

Contract Term

January 2026 - March 2026

Renewal Date

2026-03-31

Renewal Info

Change order amends original August 2025 approval. No mention of contract extension/renewal.

More from CHASSE BUILDING TEAM

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free