MWH progresses Booster Pump Station contract
Trusted by teams at
Description
MWH continues construction of the Phase 1B Booster Pump Station under a $19,706,258.71 contract with substantial completion scheduled for March 18, 2024. The project is nearly 15% complete and reported as on schedule.
Contract Details
Contract Amount
$19,706,258.71
Vendor
MWH
Agency
ALLIANCE REGIONAL WATER AUTHORITY, TX
Contract Type
CONSTRUCTION
Document Date
October 8, 2025
Contract Term
Notice to Proceed 10/25/2021; current substantial completion 3/18/2024; final completion not stated
Renewal Date
2024-03-18
Renewal Info
Contract schedule currently shows substantial completion March 18, 2024, matching program expectations; no amendments are described.
More from MWH
More from ALLIANCE REGIONAL WATER AUTHORITY
Alliance Regional Water Authority Board Member Packet 2026-05-27
Alliance Regional Water Authority Board Member Packet 2026-05-27
Alliance Regional Water Authority Board Member Packet 2026-05-27
Alliance Regional Water Authority Board Member Packet 2026-05-27
Alliance Regional Water Authority Board Member Packet 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.