CONSTRUCTIONPENDING

Stockton East Water District Agenda Packet 2026-05-26

Board Weighs $1.45M Bellota Weir Change Order

Estimated savings of $1,445,769 (change order reduction)Stockton-East Water DistrictSHIMMICK CONSTRUCTIONMay 26, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Stockton East Water District is considering a change order with Shimmick Construction to eliminate stone columns and pipe piles along specified Bellota Weir project pipelines, generating an estimated $1.45 million in savings. The adjustment balances seismic risk management with fiscal responsibility while keeping overall costs within contingency.

Contract Details

Contract Amount

Estimated savings of $1,445,769 (change order reduction)

Vendor

SHIMMICK CONSTRUCTION

Agency

Stockton-East Water District, CA

Contract Type

CONSTRUCTION

Document Date

May 26, 2026

Renewal Info

If approved, this change order will amend the existing Bellota Weir Modifications construction contract by removing stone column and pipe pile work from designated pipeline segments and reducing the contract value by approximately $1.45 million.

More from SHIMMICK CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free