Pasadena Unified School District Board Report Approval and Acceptance of the Notice of Completion for the Pasadena High School Campus Identity Project 2026-03-26

Board Authorizes $552K in PHS Project Change Orders

$552,835.01 (not-to-exceed change order amount including $50,000 contingency)Pasadena UnifiedNAZERIAN GROUPMarch 26, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Pasadena Unified School District approved Resolution No. 2816 authorizing up to $552,835.01 in change orders with The Nazerian Group for the Pasadena High School Campus Identity Project. The additional work covers fascia painting, shade structures and railings, and concrete slab removal and replacement, with a $50,000 contingency funded by Measure O bonds.

Contract Details

Contract Amount

$552,835.01 (not-to-exceed change order amount including $50,000 contingency)

Vendor

NAZERIAN GROUP

Agency

Pasadena Unified, CA

Contract Type

CONSTRUCTION

Document Date

March 26, 2026

Renewal Info

Change orders authorized under Resolution No. 2816 increase the original project contract by up to $552,835.01, including a contingency allowance for unforeseen conditions, exceeding 10% of the original bid.