The South Tangipahoa Parish Port Commission approved Change Order #3 with L King Company, LLC for up to $14,300 to repair four additional rafter beams on Warehouse Building #2. The amendment brings the total project cap to $624,387 and extends the completion date to September 29, 2023.
Contract Details
Contract Amount
Not to exceed $14,300.00 (change order); new total project amount not to exceed $624,387.00
Vendor
L KING COMPANY LLC
Agency
South Tangipahoa MPO, LA
Contract Type
CONSTRUCTION
Document Date
September 10, 2025
Contract Term
Project completion date extended 5 days to September 29, 2023
Renewal Date
2023-09-29
Renewal Info
Change order #3 adds scope for four rafter beams and extends time by 5 days; total contract cap now $624,387.00.
More from L KING COMPANY LLC
More from South Tangipahoa MPO
South Tangipahoa Parish Port Commission Minutes Regular Meeting 2026-04-08
South Tangipahoa Parish Port Commission Minutes Regular Meeting 2026-04-08
South Tangipahoa Parish Port Commission Minutes Regular Meeting 2026-04-08
South Tangipahoa Parish Port Commission Minutes Regular Meeting 2026-04-08
South Tangipahoa Parish Port Commission Minutes Regular Meeting 2026-04-08
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.