City of Dixon Staff Report HSIP Cycle 10 Pedestrian Improvements Acceptance 2026-03-17

Dixon Approves Change Order and Finalizes MCE Pedestrian Project

$220,254.75 (original) + $6,240.00 (Change Order #1) = $226,494.75 total; final invoice $215,170.01 with $161,170.01 to be paid, $11,324.74 retention, and $54,000 liquidated damages withheldCity of DixonMCE CORPORATIONMarch 17, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Dixon amended its construction agreement with MCE Corporation for the HSIP Cycle 10 Pedestrian Improvements Project, approving Contract Change Order #1 that adds $6,240 for additional surface treatment and brings the total contract to $226,494.75. The City will withhold $54,000 in liquidated damages for project delays and process a partial final payment of $161,170.01, with retention released after the statutory period following project acceptance.

Contract Details

Contract Amount

$220,254.75 (original) + $6,240.00 (Change Order #1) = $226,494.75 total; final invoice $215,170.01 with $161,170.01 to be paid, $11,324.74 retention, and $54,000 liquidated damages withheld

Vendor

MCE CORPORATION

Agency

City of Dixon, CA

Contract Type

CONSTRUCTION

Document Date

March 17, 2026

Contract Term

Notice to Proceed July 15, 2024; contract required completion within 20 working days; actual completion deemed May 16, 2025

Renewal Date

2025-05-16

Renewal Info

Not a renewable services contract; this is a one-time construction project with a fixed completion requirement. Liquidated damages of $1,000 per calendar day were applied for 54 days of delay and offset against the final payment. Retention of $11,324.74 will be released no sooner than 35 days after City Council acceptance of the work per contract terms.