Monterey One Water Board of Directors Meeting Minutes January 2026

Royal Electric Contract Amended for Electrical Upgrades

$638,471 (change order); contingency increased by $1,301,529; base contract $29,489,000; total contingency now $2,940,000Monterey One WaterROYAL ELECTRICJanuary 26, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Monterey One Water Board approved a $638,471 change order and increased the contingency by $1,301,529 for Royal Electric's contract on the CP310 Regional Treatment Plant Electrical Upgrade and Interconnection Project.

Contract Details

Contract Amount

$638,471 (change order); contingency increased by $1,301,529; base contract $29,489,000; total contingency now $2,940,000

Vendor

ROYAL ELECTRIC

Agency

Monterey One Water, CA

Contract Type

CONSTRUCTION

Document Date

January 26, 2026

Renewal Info

Change order #3 approved and contingency raised; two prior change orders detailed.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free