Key Largo Wastewater Treatment District AgendaPacket Collection System Monitoring CO #8 2026-06-02

KLWTD Amends Flovac Contract for System Monitoring

$204,076.76 (Change Order #8); new contract cumulative $4,881,279.20Key Largo Wastewater Treatment DistrictFLOVAC INCJune 2, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Key Largo Wastewater Treatment District approved Change Order #8 to its contract with Flovac, Inc., increasing the contract by $204,076.76 and extending the timeline by 90 days. This amendment reconciles post-warranty service costs and funds remaining monitoring system parts and services, with a new contract value of $4,881,279.20 and a completion date of July 21, 2026.

Contract Details

Contract Amount

$204,076.76 (Change Order #8); new contract cumulative $4,881,279.20

Vendor

FLOVAC INC

Agency

Key Largo Wastewater Treatment District, FL

Contract Type

CONSTRUCTION

Document Date

June 2, 2026

Contract Term

90 calendar day extension; new completion date July 21, 2026

Renewal Date

2026-07-21

Renewal Info

Original contract plus eight change orders, now totaling $4,881,279.20. Contract time extended to July 21, 2026. This amendment reconciles prior service support and adds new parts/service.