Change Order #1 Approved for Allgyer Enterprise, Increasing Project Budget
Trusted by teams at
Description
Borough Council approved Change Order #1 with Allgyer Enterprise, LLC, increasing the Pressure Reducing Vault – Mountain Road contract by $13,121.60 due to unforeseen site conditions and extending the completion date.
Contract Details
Contract Amount
$13,121.60 (CO#1 increase); new total $205,871.60
Vendor
ALLGYER ENTERPRISE LLC
Agency
Borough of Alburtis, PA
Contract Type
CONSTRUCTION
Document Date
May 27, 2026
Contract Term
Original: to October 18, 2025. Amended: substantial completion by December 1, 2025; final payment by May 31, 2025 (likely typo; closeout actually May 2026).
Renewal Date
2025-12-01
Renewal Info
First and only (to date) change order. Amended contract price and extended contract times.
More from ALLGYER ENTERPRISE LLC
More from Borough of Alburtis
Borough of Alburtis AgendaPacket 2026-06-10
Borough of Alburtis AgendaPacket 2026-06-10
Borough of Alburtis AgendaPacket 2026-06-10
Borough of Alburtis AgendaPacket Council Meeting 2026-05-27
Borough of Alburtis AgendaPacket Council Meeting 2026-05-27
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.