CONSTRUCTIONAMENDED

Hutter Contract Extended by Initial Change Order

Hutter, the general contractor for the Community Center, has an executed Change Order 1 extending substantial completion from August 31 to October 10 due to asbestos abatement delays. A second change order with additional financial items and requested time extensions is under review pending critical path schedule justification.

Status
AMENDED
Document date
June 17, 2026
Contract type
CONSTRUCTION
Vendor
HUTTER
Agency
Lincoln School District · MA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Original substantial completion August 31; extended to October 10 by Change Order 1; contractor-proposed completion around December 14
Renewal
Change Order 1 executed to extend substantial completion to October 10; Change Order 2 under negotiation for financial items, with schedule extensions not yet approved.
Document type
Minutes
Source document
Town of Lincoln Community Center Building Committee Minutes 2026-06-17

Related contracts

Other contracts from HUTTER.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Lincoln School District?

HUTTER was awarded this construction contract by Lincoln School District, as recorded on June 17, 2026.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Town of Lincoln Community Center Building Committee Minutes 2026-06-17 (Minutes), dated June 17, 2026 from Lincoln School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does HUTTER hold?

HUTTER may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View HUTTER's profile

What is Lincoln School District currently buying?

Explore Lincoln School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Lincoln School District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free