Change Order Adds Safety Grates to Lift Stations
Trusted by teams at
Description
The City of Mapleton issued Change Order No. 3 to CC Steel, LLC adding $4,969.50 for safety grate and latch retrofits on several sanitary lift stations. The amendment increases the lift station improvement contract to $806,722.32 without altering the June 1, 2026 substantial completion date.
Contract Details
Contract Amount
$4,969.50
Vendor
CC STEEL LLC
Agency
City of Mapleton, ND
Contract Type
CONSTRUCTION
Document Date
December 9, 2025
Contract Term
Through July 1, 2026 (no time change)
Renewal Date
2026-07-01
Renewal Info
Original contract $791,345.00; Change Orders No. 1 and 2 added $10,407.82; Change Order No. 3 adds $4,969.50, bringing the total to $806,722.32. Contract times remain Milestone 1 November 15, 2025; Milestone 2 May 15, 2026; substantial completion June 1, 2026; final payment July 1, 2026.
More from CC STEEL LLC
More from City of Mapleton
City of Mapleton City Engineer’s Agenda 2026-05-12
City of Mapleton City Engineer’s Agenda 2026-05-12
City of Mapleton City Engineer’s Agenda 2026-05-12
City of Mapleton City Engineer’s Agenda 2026-05-12
City of Mapleton City Engineer’s Agenda 2026-05-12
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.