Lake Forest Plant Advisory Council Meeting Agenda Packet May 2026

JTR Nears Completion of $2.1M WWTP Upgrade

$2,136,717.00Harris County Mud 105JTR CONSTRUCTORS INCMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Council’s engineer reports that JTR Constructors, Inc. is nearing completion of the $2,136,717.00 WWTP Improvements – 2022 CIP Phase 1 contract, with $2,093,982.67 paid to date and 99% of work complete. Final project documentation and payment will be prepared for an upcoming meeting.

Contract Details

Contract Amount

$2,136,717.00

Vendor

JTR CONSTRUCTORS INC

Agency

Harris County Mud 105, TX

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Contract Term

450 calendar days ending October 9, 2025

Renewal Date

2025-10-09

Renewal Info

Construction contract includes Change Orders 1, 2, and 3; the original duration is 450 calendar days through October 9, 2025. No formal extension or renewal terms are noted, but substantial completion occurred later with punch list closeout by May 2026.