Sowers Reconstruction Change Order Approved for Construct 1
Trusted by teams at
Description
The Board is asked to approve Change Order #01 for Construct 1 One Corporation on the Sowers Reconstruction Project, reallocating $429,751 from contingency for extended overhead due to schedule delays. The amendment maintains the overall GMP while extending the anticipated completion date to May 1, 2025.
Contract Details
Contract Amount
$49,704,502.00 original value; Change Order reduces contingency by $429,751
Vendor
CONSTRUCT 1 ONE CORPORATION
Agency
Huntington Beach City Elementary, CA
Contract Type
CONSTRUCTION
Document Date
November 18, 2025
Contract Term
Initial completion date November 1, 2024; new anticipated completion date May 1, 2025
Renewal Date
2025-05-01
Renewal Info
Change Order #01 utilizes $429,751 of the original 5% construction contingency for extended overhead associated with 92 compensable delay days, with any unused contingency reverting to the District at project completion.
More from CONSTRUCT 1 ONE CORPORATION
More from Huntington Beach City Elementary
Huntington Beach City School District Board Meeting Agenda May 2026
Huntington Beach City School District Board Meeting Agenda May 2026
Huntington Beach City School District Board Meeting Agenda May 2026
Huntington Beach City School District Board Meeting Agenda May 2026
Huntington Beach City School District Board Meeting Agenda May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.