Additional Roof Work Approved With Garland/DBS

$18,580.00 (additional); revised total $171,731.00Town of SanduskyGARLAND/DBS INCMay 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Sandusky approved an additional $18,580 to Garland/DBS Inc. through a cooperative purchasing program for added roof and façade repairs at the Big Island Water Works clarifier building, bringing the total project cost to $171,731. The work covers materials, mobilization, installation, and warranty.

Contract Details

Contract Amount

$18,580.00 (additional); revised total $171,731.00

Vendor

GARLAND/DBS INC

Agency

Town of Sandusky, OH

Contract Type

CONSTRUCTION

Document Date

May 23, 2026

Renewal Info

Change to existing facilities contract via U.S. Communities cooperative, increasing scope and not-to-exceed amount for BIWW clarifier building roof and façade.