CONSTRUCTIONAMENDED

Sidewalk Project Contract Amended for Final Payment

The Ladd Village Board approved Change Order #3 and the final payment request with Gillan Construction for the Main Avenue Sidewalk Project, increasing the contract by $6,513.50 to a final total of $121,825.00. The action authorizes payment of the remaining $40,768.23 due under the project.

Status
AMENDED
Document date
December 23, 2025
Contract type
CONSTRUCTION
Vendor
Gillan Construction
Agency
Ladd village · IL

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Increase of $6,513.50; total final cost $121,825.00; remaining to be paid $40,768.23
Contract type
CONSTRUCTION
Renewal
Change Order #3 establishes the final contract amount of $121,825.00 for the Main Avenue Sidewalk Project.
Document type
Minutes
Source document
Ladd Village Board Meeting Minutes December 2025

Related contracts

Other contracts from Gillan Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Ladd village?

Gillan Construction was awarded this construction contract by Ladd village, as recorded on December 23, 2025. The contract value is Increase of $6,513.50; total final cost $121,825.00; remaining to be paid $40,768.23.

How much is the Gillan Construction contract with Ladd village worth?

The Gillan Construction contract with Ladd village is valued at Increase of $6,513.50; total final cost $121,825.00; remaining to be paid $40,768.23, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Ladd Village Board Meeting Minutes December 2025 (Minutes), dated December 23, 2025 from Ladd village. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Gillan Construction hold?

Gillan Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Gillan Construction's profile

What is Ladd village currently buying?

Explore Ladd village's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Ladd village's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free