Change Order Reduces Cost, Extends Schedule for Keller Excavating
Trusted by teams at
Description
Ames City Council will approve Change Order No. 7 with Keller Excavating, Inc. for the North River Valley Well Field and Pipeline Project, reducing the contract by $505,353.34 and extending substantial and final completion dates by roughly 7 months. The amendment adjusts both cost and schedule for the ongoing construction project.
Contract Details
Contract Amount
-$505,353.34 (deduct change order)
Vendor
KELLER EXCAVATING INC
Agency
City of Ames, IA
Contract Type
CONSTRUCTION
Document Date
June 23, 2026
Contract Term
Project dates extended by 209–212 days
Renewal Info
Seventh change order deducting $505,353.34 and extending substantial completion by 209 days and final completion by 212 days; new total contract amount is not listed in the agenda.
More from KELLER EXCAVATING INC
More from City of Ames
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.