Clay Township Adds $1.27M to M-29 Water Main Contract
Trusted by teams at
Description
Clay Township approved Change Order No. 1 with Pamar Enterprises, Inc. for the M-29 Water Main Improvements project, increasing the construction contract by $1,270,074.10 to a new total of $9,522,259.10. The amendment covers wage rate increases and BABA-compliant materials required for a $2.5 million grant, with no change to scheduled completion dates in September and October 2026.
Contract Details
Contract Amount
Increase of $1,270,074.10 (new total $9,522,259.10)
Vendor
PAMAR ENTERPRISES INC
Agency
Town of Clay, MI
Contract Type
CONSTRUCTION
Document Date
May 5, 2026
Contract Term
No change; substantial completion Sept. 15, 2026; final payment Oct. 1, 2026
Renewal Date
2026-10-01
Renewal Info
Change Order No. 1 amends the July 1, 2025 construction contract price only; contract completion dates remain at September 15, 2026 for substantial completion and October 1, 2026 for final payment.
More from PAMAR ENTERPRISES INC
More from Town of Clay
Clay Township Insurance Proposal 2026-07-01
Clay Township Insurance Proposal 2026-07-01
Clay Township Insurance Proposal 2026-07-01
Clay Township Insurance Proposal 2026-07-01
Clay Township Insurance Proposal 2026-07-01
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.