CONSTRUCTIONAMENDED

Gregg County CTIF Contract Change Order Form 2025-02-05

Bridge project change order reduces contract amount

$166,474.00 (original $167,265.00; net decrease $791.00)Gregg CountyWMS R AND B LLCFebruary 5, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Gregg County approved Change Order No. 1 with WMS R and B, LLC for the CTIF Spinks-Chapman Bridge/Guard Rail project, decreasing the contract by $791 while adding milling work and maintaining the original 60-day schedule. The revised contract price is $166,474 for work running from January 13, 2025 through March 14, 2025.

Contract Details

Contract Amount

$166,474.00 (original $167,265.00; net decrease $791.00)

Vendor

WMS R AND B LLC

Agency

Gregg County, TX

Contract Type

CONSTRUCTION

Document Date

February 5, 2025

Contract Term

Construction Contract Start Date: 1/13/2025; Construction Contract End Date: 3/14/2025; duration 60 calendar days

Renewal Date

2025-03-14

Renewal Info

Change Order No. 1 adjusts pay items and reduces the total contract value by $791 without altering the 60-day contract duration or the March 14, 2025 completion date. No renewal or extension options are referenced in the document.