Gregg County approved Change Order No. 1 with WMS R and B, LLC for the CTIF Spinks-Chapman Bridge/Guard Rail project, decreasing the contract by $791 while adding milling work and maintaining the original 60-day schedule. The revised contract price is $166,474 for work running from January 13, 2025 through March 14, 2025.
Contract Details
Contract Amount
$166,474.00 (original $167,265.00; net decrease $791.00)
Vendor
WMS R AND B LLC
Agency
Gregg County, TX
Contract Type
CONSTRUCTION
Document Date
February 5, 2025
Contract Term
Construction Contract Start Date: 1/13/2025; Construction Contract End Date: 3/14/2025; duration 60 calendar days
Renewal Date
2025-03-14
Renewal Info
Change Order No. 1 adjusts pay items and reduces the total contract value by $791 without altering the 60-day contract duration or the March 14, 2025 completion date. No renewal or extension options are referenced in the document.
More from WMS R AND B LLC
More from Gregg County
Gregg County Commissioners' Court Agenda 2026-05-26
Gregg County Commissioners' Court Agenda 2026-05-26
Gregg County Commissioners' Court Agenda 2026-05-26
Gregg County Commissioners' Court Agenda 2026-05-26
Gregg County Commissioners' Court Agenda 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.