CONSTRUCTIONAMENDED

City Amends Moyle Contract for Meter Project Savings

The City of Angels is amending its Water Meter Replacement Project Phase 1 and Phase 2 contract with Moyle Excavation, Inc. through Construction Change Order No. 003, reallocating savings from lower-than-estimated meter work to replace seven deteriorated water service laterals and restore pavement, while still yielding a $106,656 credit to the project budget. The original construction contract was $795,257, with previous change orders for service laterals and oversized meters.

Status
AMENDED
Document date
August 3, 2026
Contract type
CONSTRUCTION
Vendor
Moyle Excavation Inc
Agency
City of Angels · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Original contract $795,257; Change Order 001 $32,840; Change Order 002 $68,678; Change Order 003 credit ($106,656.00) including $101,700.00 for seven service lateral replacements
Contract type
CONSTRUCTION
Renewal
Construction Change Order No. 003 reduces certain meter replacement quantities, adds seven water service lateral replacements and associated pavement restoration and mobilization, and results in a net credit of $106,656. It follows Change Order 001 for Phase 1 lateral replacements and Change Order 002 for oversized meters.
Document type
AgendaPacket
Source document
City of Angels AgendaPacket City Council Meeting 2026-08-04

Related contracts

Other contracts from Moyle Excavation Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Angels?

Moyle Excavation Inc was awarded this construction contract by City of Angels, as recorded on August 3, 2026. The contract value is Original contract $795,257; Change Order 001 $32,840; Change Order 002 $68,678; Change Order 003 credit ($106,656.00) including $101,700.00 for seven service lateral replacements.

How much is the Moyle Excavation Inc contract with City of Angels worth?

The Moyle Excavation Inc contract with City of Angels is valued at Original contract $795,257; Change Order 001 $32,840; Change Order 002 $68,678; Change Order 003 credit ($106,656.00) including $101,700.00 for seven service lateral replacements, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of Angels AgendaPacket City Council Meeting 2026-08-04 (AgendaPacket), dated August 3, 2026 from City of Angels. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Moyle Excavation Inc hold?

Moyle Excavation Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Moyle Excavation Inc's profile

What is City of Angels currently buying?

Explore City of Angels's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Angels's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free