Change order for Plano West Side Pipeline project
Trusted by teams at
Description
NTMWD proposes Change Order No. 2 with S.J. Louis Construction of Texas, Ltd. adding $251,568 and 60 days to the Plano West Side Pipeline contract to adjust tunneling depth and avoid a fiber optic conflict beneath the DART Silverline right-of-way. The change increases the total contract value to $18.85 million and extends completion to late 2026.
Contract Details
Contract Amount
$251,568.00
Vendor
S.J. LOUIS CONSTRUCTION OF TEXAS LTD
Agency
NORTH MONTAGUE COUNTY WATER SUPPLY DISTRICT, TX
Contract Type
CONSTRUCTION
Document Date
April 23, 2026
Contract Term
Change Order No. 2 adds 60 days, extending substantial completion to October 26, 2026 and final completion to December 25, 2026
Renewal Date
2026-12-25
Renewal Info
Change Order No. 2 extends substantial completion from August 18, 2026 to October 26, 2026 and final completion from October 17, 2026 to December 25, 2026.
More from S.J. LOUIS CONSTRUCTION OF TEXAS LTD
Issuing Agency
Utility District
Nocona, TX
More from NORTH MONTAGUE COUNTY WATER SUPPLY DISTRICT
North Texas Municipal Water District Board of Directors Meeting Agenda April 2026
North Texas Municipal Water District Board of Directors Meeting Agenda April 2026
North Texas Municipal Water District Board of Directors Meeting Agenda April 2026
North Texas Municipal Water District Board of Directors Meeting Agenda April 2026
North Texas Municipal Water District Board of Directors Meeting Agenda April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.