CONSTRUCTIONAMENDED

North Texas Municipal Water District Board of Directors Agenda April 2026

Change order for Plano West Side Pipeline project

$251,568.00NORTH MONTAGUE COUNTY WATER SUPPLY DISTRICTS.J. LOUIS CONSTRUCTION OF TEXAS LTDApril 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

NTMWD proposes Change Order No. 2 with S.J. Louis Construction of Texas, Ltd. adding $251,568 and 60 days to the Plano West Side Pipeline contract to adjust tunneling depth and avoid a fiber optic conflict beneath the DART Silverline right-of-way. The change increases the total contract value to $18.85 million and extends completion to late 2026.

Contract Details

Contract Amount

$251,568.00

Vendor

S.J. LOUIS CONSTRUCTION OF TEXAS LTD

Agency

NORTH MONTAGUE COUNTY WATER SUPPLY DISTRICT, TX

Contract Type

CONSTRUCTION

Document Date

April 23, 2026

Contract Term

Change Order No. 2 adds 60 days, extending substantial completion to October 26, 2026 and final completion to December 25, 2026

Renewal Date

2026-12-25

Renewal Info

Change Order No. 2 extends substantial completion from August 18, 2026 to October 26, 2026 and final completion from October 17, 2026 to December 25, 2026.