CONSTRUCTIONONGOING

Garberville Sanitary District Board Meeting Agenda September 2025

Tank Replacement Project: Wahlund Construction Change Order

$3,686,400 (original); $3,652,473 (with change orders); CCO#7 estimated at $6,800 additionalGarberville Sanitary DistrictWAHLUND CONSTRUCTIONSeptember 23, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Garberville Sanitary District continues construction with Wahlund Construction on the Tank Replacement Project. Change Order 7 is in progress for $6,800 to install an additional man gate and bollards at the Wallan Tank site.

Contract Details

Contract Amount

$3,686,400 (original); $3,652,473 (with change orders); CCO#7 estimated at $6,800 additional

Vendor

WAHLUND CONSTRUCTION

Agency

Garberville Sanitary District, CA

Contract Type

CONSTRUCTION

Document Date

September 23, 2025

Renewal Date

2025-12-31

Renewal Info

Change orders executed as needed; CCO#7 underway. Contract aligns with project schedule and contingency.