CONSTRUCTIONAMENDED

Oakland Unified School District Agenda 2026-06-24

Play yard improvement contract term extended

Aspire Berkley Maynard Academy DistrictGUITERREZ, NICHOLAS DBA N G BUILDER COMPANYJune 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board approved a term extension for Nicholas Guiterrez dba N G Builder Company on the Harriet Tubman Child Development Center play yard improvement project. The contract completion date is extended by 59 days to June 30, 2026, with all other terms unchanged.

Contract Details

Vendor

GUITERREZ, NICHOLAS DBA N G BUILDER COMPANY

Agency

Aspire Berkley Maynard Academy District, CA

Contract Type

CONSTRUCTION

Document Date

June 23, 2026

Contract Term

Extended from February 16, 2026 – May 2, 2026 to June 30, 2026 (additional 59 calendar days)

Renewal Date

2026-06-30

Renewal Info

Change Order No. 1 extends the completion date to June 30, 2026; all other terms remain unchanged.