CONSTRUCTIONAMENDED

Mountain Line Board Meeting Agenda Packet October 2025

Loven Contracting GMP Added for DCC Utility Relocation

$1,635,504.59 (GMP #4); cumulative total $27,126,241.29Northern Arizona Intergovernmental Public Transportation AuthorityLOVEN CONTRACTINGOctober 15, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Mountain Line executed Amendment #5 with Loven Contracting establishing GMP #4 at $1,635,504.59 for underground relocation of APS, Optimum, and Lumen utilities at the Downtown Connection Center site. This change brings the CMAR contract total to $27.1 million and advances both Phase 1 completion and future Phase 2b operations hub development.

Contract Details

Contract Amount

$1,635,504.59 (GMP #4); cumulative total $27,126,241.29

Vendor

LOVEN CONTRACTING

Agency

Northern Arizona Intergovernmental Public Transportation Authority, AZ

Contract Type

CONSTRUCTION

Document Date

October 15, 2025

Contract Term

CMAR contract awarded March 2022; GMP #4 added October 2025 for Phase 1 and Phase 2b utility relocation

Renewal Info

CMAR contract is being implemented through multiple GMP amendments; GMP #4 expands scope for third-party utility relocation as part of phased project delivery.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free