CONSTRUCTIONAMENDED

Unused allowance credited via deductive change order

San José Evergreen Community College District issued Prime Contract Change Order #008 with Flint Design Build LLC dba Flint to deduct $1,110,557.89 in unused allowance for the Career Education Complex project. The change reduces the contract amount to $145,080,057.11 without altering the December 31, 2025 completion date.

Status
AMENDED
Document date
March 24, 2026
Contract type
CONSTRUCTION
Vendor
Flint Design Build Llc Dba Flint
Agency
San Jose-Evergreen Community College District · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
($1,110,557.89) (deductive change order); Original Contract Amount $140,326,519.00; New Contract Amount $145,080,057.11
Contract type
CONSTRUCTION
Contract term
Contract Date: 11/10/2021; Original Completion Date 12/31/2025; Revised Completion Date 12/31/2025
Renewal date
2025-12-31
Renewal
Prime Contract Change Order #008 (PCO #92) is a deductive change removing unused allowance and does not extend contract time; original and revised completion dates remain 12/31/2025.
Document type
Contract
Source document
San José Evergreen Community College District Contract Prime Contract Change Order 2026-03-24

Related contracts

Other contracts from Flint Design Build Llc Dba Flint.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by San Jose-Evergreen Community College District?

Flint Design Build Llc Dba Flint was awarded this construction contract by San Jose-Evergreen Community College District, as recorded on March 24, 2026. The contract value is ($1,110,557.89) (deductive change order); Original Contract Amount $140,326,519.00; New Contract Amount $145,080,057.11.

How much is the Flint Design Build Llc Dba Flint contract with San Jose-Evergreen Community College District worth?

The Flint Design Build Llc Dba Flint contract with San Jose-Evergreen Community College District is valued at ($1,110,557.89) (deductive change order); Original Contract Amount $140,326,519.00; New Contract Amount $145,080,057.11, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in San José Evergreen Community College District Contract Prime Contract Change Order 2026-03-24 (Contract), dated March 24, 2026 from San Jose-Evergreen Community College District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Flint Design Build Llc Dba Flint hold?

Flint Design Build Llc Dba Flint may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Flint Design Build Llc Dba Flint's profile

What is San Jose-Evergreen Community College District currently buying?

Explore San Jose-Evergreen Community College District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View San Jose-Evergreen Community College District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free