Change Order Adds Waterproofing To WWTP Project
Trusted by teams at
Description
The City of Carroll approved Change Order No. 3 with Blue Ribbon Builders, LLC for the WWTP Digester & VLR Air Piping Improvements project, adding $163,416.75 for installation of a Sika 7600 waterproofing system in Digester 2. The change raises the total contract to $3,202,095.00 and extends project completion to late September 2026.
Contract Details
Contract Amount
$163,416.75
Vendor
BLUE RIBBON BUILDERS LLC
Agency
City of Carroll, IA
Contract Type
CONSTRUCTION
Document Date
April 15, 2026
Contract Term
Contract time extended 90 days; Plant in full operation by August 29, 2026 and all work complete by September 28, 2026
Renewal Date
2026-09-28
Renewal Info
Third change order to original WWTP Digester & VLR Air Piping Improvements construction contract; cumulative approved change orders total $205,095.00 and extend the contract duration by 90 days.
More from BLUE RIBBON BUILDERS LLC
More from City of Carroll
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.