Huntertown Town Council AgendaPacket Meeting Agenda and Supporting Documents 2026-06-15

Change Order Cuts Pulver Street Contract, Extends Dates

Decrease of $94,755.90 (new contract price $1,912,136.10)Town of Huntertown townPULVER ASPHALT PAVING INCJune 15, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Huntertown processed Change Order No. 02 with Pulver Asphalt Paving, Inc. on the CCMG 2024-02 Hunter Park Street Improvements contract, reducing the contract amount by $94,755.90 to $1,912,136.10. The change order also extended substantial completion to June 12, 2026 and final payment readiness to June 26, 2026.

Contract Details

Contract Amount

Decrease of $94,755.90 (new contract price $1,912,136.10)

Vendor

PULVER ASPHALT PAVING INC

Agency

Town of Huntertown town, IN

Contract Type

CONSTRUCTION

Document Date

June 15, 2026

Contract Term

Substantial Completion extended to June 12, 2026; Final payment readiness June 26, 2026

Renewal Date

2026-06-26

Renewal Info

Second change order on the contract, decreasing scope and extending completion deadlines to June 12 and June 26, 2026.