Wyndham Park Project Gets 39-Day No-Cost Extension
Trusted by teams at
Description
Woolwich Township granted Wyndham Construction, LLC a 39-day no-cost time extension via Change Order #4 for the Locke Avenue Park Development – Phase 1 project, pushing substantial completion to June 19, 2026 while keeping the contract total at $11,075,932.56. The extension addresses utility, weather, and design-related delays.
Contract Details
Contract Amount
Original contract $9,872,294.85; Change Orders #1-3 increased total to $11,075,932.56; Change Order #4 adds 39 days with no cost change (final amount $11,075,932.56)
Vendor
WYNDHAM CONSTRUCTION LLC
Agency
Township of Woolwich, NJ
Contract Type
CONSTRUCTION
Document Date
June 15, 2026
Contract Term
Substantial completion date extended from May 12, 2026 to June 19, 2026
Renewal Date
2026-06-19
Renewal Info
Change Order #4 extends the substantial completion deadline to June 19, 2026 without altering the contract price; future extensions would require additional change orders.
More from WYNDHAM CONSTRUCTION LLC
More from Township of Woolwich
Woolwich Township Committee Agenda Packet 2026-06-15
Woolwich Township Committee Agenda Packet 2026-06-15
Woolwich Township Committee Agenda Packet 2026-06-15
Woolwich Township Committee Agenda Packet 2026-06-15
Woolwich Township Committee Agenda Packet 2026-06-15
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.