Tweedy Mile Street Contract Amended for Extra Work
Trusted by teams at
Description
The South Gate City Council approved two change orders with Sequel Contractors, Inc. for the Tweedy Mile Complete Streets Project, adding up to $494,793 for an accelerated schedule and final quantity reconciliation. The City also appropriated $500,000 in Proposition C funds to support the changes and related staff costs.
Contract Details
Contract Amount
Not to exceed $350,000 (Change Order No. 15); Not to exceed $144,793 (Change Order No. 16); $500,000 Proposition C funding appropriation noted for both change orders and staff time
Vendor
SEQUEL CONTRACTORS INC
Agency
City of South Gate, CA
Contract Type
CONSTRUCTION
Document Date
May 26, 2026
Renewal Info
Change Orders Nos. 15 and 16 amend Contract No. 2024-56-CC, increasing authorized funding and adjusting schedule and quantities; original term and any renewal options remain as in the base contract.
More from SEQUEL CONTRACTORS INC
More from City of South Gate
City of South Gate Agenda 2026-05-26
City of South Gate Agenda Bill Agreement with Danny Letner Inc. 2026-05-26
City of South Gate Agenda Item No. 19 2026-05-26
City of South Gate Agenda Special Joint City Council/Housing Authority Meeting 2026-05-26
City of South Gate Minutes Approval of City Council and South Gate Housing Authority Meeting Minutes 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.