CONSTRUCTIONPENDING

Lift Station 13 material change order with Mainline

Mexico Beach is reviewing Change Order No. 6 with Mainline Construction for the 14th Street Lift Station project, adding $6,178.60 to change piping materials at Lift Station 13 and extending the contract by three days. The amendment increases the total contract value to $1,057,392.33 while remaining within previously realized project savings.

Status
PENDING
Document date
June 29, 2026
Contract type
CONSTRUCTION
Vendor
Mainline Construction
Agency
City of Mexico Beach · FL

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$6,178.60 (change order); new total contract $1,057,392.33
Contract type
CONSTRUCTION
Contract term
Original dates: 05/14/25 – 10/11/25; Change Order No. 6 adds 3 days
Renewal
Change Order No. 6 adds $6,178.60 and 3 additional days to the existing 14th Street Lift Station construction contract, increasing cumulative change orders to $257,996.36 and the total contract to $1,057,392.33. Base substantial and final completion dates of 09/11/25 and 10/11/25 are extended by 3 days, but the adjusted dates are not explicitly calculated in the document.
Document type
AgendaPacket
Source document
City of Mexico Beach AgendaPacket City Council Workshop 2026-06-29

Related contracts

Other contracts from Mainline Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Mexico Beach?

Mainline Construction was awarded this construction contract by City of Mexico Beach, as recorded on June 29, 2026. The contract value is $6,178.60 (change order); new total contract $1,057,392.33.

How much is the Mainline Construction contract with City of Mexico Beach worth?

The Mainline Construction contract with City of Mexico Beach is valued at $6,178.60 (change order); new total contract $1,057,392.33, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of Mexico Beach AgendaPacket City Council Workshop 2026-06-29 (AgendaPacket), dated June 29, 2026 from City of Mexico Beach. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Mainline Construction hold?

Mainline Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Mainline Construction's profile

What is City of Mexico Beach currently buying?

Explore City of Mexico Beach's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Mexico Beach's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free