Rockdale Amends Meadow Avenue Watermain Contract
Trusted by teams at
Description
The Village of Rockdale approved Change Order No. 2 with Austin Tyler Construction, Inc. for the Meadow Avenue Watermain Replacement Project, adding $99,641.70 and extending completion to August 29, 2026. The amendment reflects additional work associated with concrete and manhole cover removal issues that affected cost and schedule.
Contract Details
Contract Amount
$99,641.70 (increase); new total $3,905,061.58
Vendor
AUSTIN TYLER CONSTRUCTION INC
Agency
Rockdale village, IL
Contract Type
CONSTRUCTION
Document Date
May 19, 2026
Contract Term
Contract Completion date extended 29 days from July 31, 2026 to August 29, 2026
Renewal Date
2026-08-29
Renewal Info
Change Order No. 2 increases the contract sum and extends the project completion date by 29 days to August 29, 2026.
More from AUSTIN TYLER CONSTRUCTION INC
More from Rockdale village
Rockdale Village Board Meeting Agenda 2026-06-02
Rockdale Village Board Meeting Agenda 2026-06-02
Rockdale Village Board Meeting Agenda 2026-06-02
Village of Rockdale Board Meeting Minutes 2026-05-19
Village of Rockdale Board Meeting Minutes 2026-05-19
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.