Change order boosts CVHS music door project cost and time
Trusted by teams at
Description
Glendale Unified will ratify a $3,430.06 change order with AMB Group Inc. for Crescenta Valley High School’s music building door replacement project. The amendment addresses unexpected concrete work, raising the contract total to $42,880.06 and extending completion by three days under Proposition 28 funding.
Contract Details
Contract Amount
$3,430.06 (new total $42,880.06)
Vendor
AMB GROUP INC
Agency
Glendale Unified, CA
Contract Type
CONSTRUCTION
Document Date
May 19, 2026
Contract Term
Contract time increased by 3 days for a total of 59 days, with completion date of May 3, 2026
Renewal Date
2026-05-03
Renewal Info
Change Order No. 1 increases the original $39,450 contract by 8.69% and extends contract time from 56 to 59 days; no additional renewals or options are mentioned.
More from AMB GROUP INC
More from Glendale Unified
Glendale Unified School District AgendaPacket Board of Education Meeting 2026-05-19
Glendale Unified School District AgendaPacket Board of Education Meeting 2026-05-19
Glendale Unified School District AgendaPacket Board of Education Meeting 2026-05-19
Glendale Unified School District AgendaPacket Board of Education Meeting 2026-05-19
Glendale Unified School District AgendaPacket Board of Education Meeting 2026-05-19
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.