Board of Public Works Regular Meeting Agenda April 2026

Budget increased for PCL pumping plant rehab

Not-to-exceed $682,483 (Change Order No. 20); revised construction budget $7,074,801City of Los Angeles - LA Sanitation and EnvironmentPCL CONSTRUCTION INCApril 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board of Public Works amended its construction contract with PCL Construction, Inc. for the Harris Place Pumping Plant 669 Rehabilitation project, increasing the construction budget to $7,074,801. A supplemental change order of up to $682,483 was approved to address delay-related work on meter pit hatches, wet well baffles, coatings, and level switches.

Contract Details

Contract Amount

Not-to-exceed $682,483 (Change Order No. 20); revised construction budget $7,074,801

Vendor

PCL CONSTRUCTION INC

Agency

City of Los Angeles - LA Sanitation and Environment, CA

Contract Type

CONSTRUCTION

Document Date

April 20, 2026

Renewal Info

Additional contingency of $906,382 approved and Supplemental Agreement Change Order No. 20 (up to $682,483) plus Change Order No. 19 issued; subsequent change orders authorized within revised budget.

More from PCL CONSTRUCTION INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free