Walsh AWPF Construction Contract Schedules NTP In May
Trusted by teams at
Description
Walsh is under contract to construct the Advanced Water Purification Facility for $60,175,879. The project will commence with a Notice to Proceed on May 4, 2026, and is scheduled for substantial completion by December 19, 2028 and final completion by February 17, 2029.
Contract Details
Contract Amount
$60,175,879.00
Vendor
WALSH
Agency
Carpinteria Sanitary District, CA
Contract Type
CONSTRUCTION
Document Date
April 28, 2026
Contract Term
Notice to Proceed May 4, 2026; Substantial Completion by December 19, 2028 (960 calendar days); Final Completion by February 17, 2029 (1,020 calendar days)
Renewal Date
2029-02-17
Renewal Info
Baseline construction period is 1,020 calendar days from Notice to Proceed; no extensions or change orders have been approved yet.
More from WALSH
More from Carpinteria Sanitary District
Carpinteria Sanitary District Governing Board Special Meeting Agenda April 28, 2026
Carpinteria Sanitary District Governing Board Special Meeting Agenda April 28, 2026
Carpinteria Sanitary District Governing Board Special Meeting Agenda April 28, 2026
Carpinteria Sanitary District Governing Board Special Meeting Agenda April 28, 2026
Carpinteria Sanitary District Governing Board Special Meeting Agenda April 28, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.