Major change order reduces greenhouse contract cost
Trusted by teams at
Description
Merced College trustees ratified Change Order No. 3 with Menghetti Construction, Inc. for the Greenhouse Complex, approving a package of scope changes that reduced the contract by $163,885.00 while extending the schedule by 240 days. The greenhouse project ultimately closed on October 31, 2025 at a total cost of $1,738,789.00.
Contract Details
Contract Amount
($163,885.00) (Change Order No. 3); project total $1,738,789.00
Vendor
MENGHETTI CONSTRUCTION INC
Agency
Merced College, CA
Contract Type
CONSTRUCTION
Document Date
November 18, 2025
Contract Term
Original contract plus 240 additional days from Change Order No. 3; Notice to Proceed June 26, 2025; project completed October 31, 2025
Renewal Date
2025-10-31
Renewal Info
Third change order on Bid #2024-11, extending contract time by 240 days and decreasing the contract amount; final contract completed and accepted October 31, 2025 with Notice of Completion and retention release.
More from MENGHETTI CONSTRUCTION INC
More from Merced College
Merced College Agenda Board of Trustees Regular Meeting 2026-06-09
Merced College Agenda Board of Trustees Regular Meeting 2026-06-09
Merced College Board of Trustees Regular Meeting Agenda 2026-05-19
Merced College Board of Trustees Regular Meeting Agenda 2026-05-19
Merced College Board of Trustees Regular Meeting Agenda April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.