Close-out change order finalized for lift station project
Trusted by teams at
Description
The Parish Council approved a close-out Change Order No. 3 with Command Construction, LLC for the Ezekial Jackson and Esperanza lift station rehabilitation project. The final change order reconciles quantities, assesses $61,320 in liquidated damages for 73 days of delay, and withholds retainage such that the contractor owes the Parish $2,270.68.
Contract Details
Contract Amount
-$8,652.40 net decrease; $61,320 liquidated damages assessed; $50,396.92 retainage withheld; $2,270.68 owed to Parish
Vendor
COMMAND CONSTRUCTION LLC
Agency
St. John the Baptist Parish, LA
Contract Type
CONSTRUCTION
Document Date
April 14, 2026
Renewal Info
Close-out Change Order No. 3 reconciles final quantities, liquidated damages, and retainage, resulting in a net decrease in the contract and a balance owed to the Parish.
More from COMMAND CONSTRUCTION LLC
More from St. John the Baptist Parish
St. John the Baptist Parish Council Meeting Minutes April 14 2026
St. John the Baptist Parish Council Meeting Minutes April 14 2026
St. John the Baptist Parish Council Meeting Minutes April 14 2026
St. John the Baptist Parish Council Meeting Minutes April 14 2026
St. John the Baptist Parish Council Meeting Minutes March 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.