Solar and Battery Storage Development Contract with POW Solar LLC

Estimated Project Cost: $10,900,000 (information only, not final); Project Development Budget not to exceed $100,000; Addendum 1: Not to exceed $250,000 for 2 MVA Transformers if ordered/canceledCity of BeloitPOW SOLAR LLCFebruary 5, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Beloit City Council approved a Resolution authorizing an agreement with POW Solar, LLC for the development and preliminary procurement activities for a major solar and battery storage project, with an estimated cost of $10.9 million and a not-to-exceed $100,000 budget for project development services. The contract also allows for the early order of two 2 MVA transformers up to $250,000 if needed for Investment Tax Credit purposes. Construction is expected to follow after the development phase and final agreements.

Contract Details

Contract Amount

Estimated Project Cost: $10,900,000 (information only, not final); Project Development Budget not to exceed $100,000; Addendum 1: Not to exceed $250,000 for 2 MVA Transformers if ordered/canceled

Vendor

POW SOLAR LLC

Agency

City of Beloit, KS

Contract Type

PROFESSIONAL_SERVICES

Document Date

February 5, 2025

Contract Term

Development/Engineering starts upon agreement effective February 5, 2025, through Notice to Proceed and construction (NTP estimated 6/1/2025, COD estimated 12/31/2025), Development Services are prior to construction; Ongoing as definitive agreements are finalized

Renewal Date

2025-12-31

Renewal Info

Development phase contract. Main project agreements (EPC, O&M) to be executed after successful completion of pre-construction activities. Early transformer purchase is subject to project continuation.