Town of Coventry School Energy and Building Efficiency Committee AgendaPacket May 2026

Pro-Mech HVAC Contract Increased by Change Orders

$11,996,520 original; $474,501 total change orders; revised total $12,471,021Town of CoventryPRO-MECH INCMay 7, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Town of Coventry’s School Building Energy Efficiency HVAC project with Pro-Mech, Inc has increased from the original $11,996,520 to a revised $12,471,021 after 11 change orders. The amendments cover additional electrical, mechanical, and finish work required to complete the project.

Contract Details

Contract Amount

$11,996,520 original; $474,501 total change orders; revised total $12,471,021

Vendor

PRO-MECH INC

Agency

Town of Coventry, CT

Contract Type

CONSTRUCTION

Document Date

May 7, 2026

Renewal Info

Contract amended through Change Orders #001–#011 for a cumulative increase of $474,501, revising the total contract amount to $12,471,021.

More from PRO-MECH INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free