City of Watsonville Agenda Joint Meeting of the City Council, Successor Agency, and Successor Housing Agency 2026-05-12

Ramsay Park Construction Contract Amended and Extended

Increase of $958,523.61 for a revised total contract amount not to exceed $27,907,082.67City of WatsonvilleROBERT a BOTHMAN CONSTRUCTIONMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Watsonville approved Contract Change Order No. 9 with Robert A. Bothman Construction for the Ramsay Park Renaissance Project, adding $958,523.61 and extending the contract term to June 21, 2026. The revised construction contract now totals up to $27,907,082.67 for expanded project scope.

Contract Details

Contract Amount

Increase of $958,523.61 for a revised total contract amount not to exceed $27,907,082.67

Vendor

ROBERT a BOTHMAN CONSTRUCTION

Agency

City of Watsonville, CA

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Contract Term

Extending the contract term to June 21, 2026

Renewal Date

2026-06-21

Renewal Info

Ninth change order increases scope and compensation and extends the construction contract term to June 21, 2026.

More from ROBERT a BOTHMAN CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free