City Adds Safety Railing Change Order to Street Project
Trusted by teams at
Description
Edgerton will consider Change Order #5 with Kansas Heavy Construction LLC, adding $38,500 to install safety railing around a box culvert on the East 2nd Street/Edgewood and East 3rd Street Reconstruction Project. The contract total would rise to $5,412,437.66, funded within the existing project budget and contingency.
Contract Details
Contract Amount
$38,500.00 (Change Order #5; revised contract total $5,412,437.66)
Vendor
KANSAS HEAVY CONSTRUCTION LLC
Agency
City of Edgerton, KS
Contract Type
CONSTRUCTION
Document Date
May 28, 2026
Contract Term
Original contract performance period 433 calendar days from 2025-04-24 to 2026-06-30; term unchanged by this change order
Renewal Date
2026-06-30
Renewal Info
Fifth change order to the April 24, 2025 construction contract for East 2nd Street/Edgewood and East 3rd Street reconstruction; prior change orders #1–#4 increased the contract by $182,120.66 before this amendment.
More from KANSAS HEAVY CONSTRUCTION LLC
More from City of Edgerton
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.