Harris County Municipal Utility District No. 304 Board Meeting Minutes January 2026

Construction Pay Application Approved for Waterline Extension

$299,886.00 (current contract total), Pay Request No. 3: $146,834.10Harris County Mud 304ISJ UNDERGROUND UTILITIESJanuary 15, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The board will consider a $146,834.10 pay request (No. 3) from ISJ Underground Utilities for the 12-inch waterline extension project under a current total contract of $299,886.00. Project construction is nearing completion.

Contract Details

Contract Amount

$299,886.00 (current contract total), Pay Request No. 3: $146,834.10

Vendor

ISJ UNDERGROUND UTILITIES

Agency

Harris County Mud 304, TX

Contract Type

CONSTRUCTION

Document Date

January 15, 2026

Contract Term

July 21, 2025 – October 24, 2025 (contracted 60 days, extended/overlapping project active through January 2026)

Renewal Date

2026-01-31

Renewal Info

Original contract awarded July 2025, $270,661 (+$29,225 quantity adjustment). Anticipated closure in early 2026, no automatic renewal. One-time construction contract.