Change Order Approved For Crane Bayou Pump Station Project

$41,347.00 (change order); new total $1,590,347.00Jefferson CountyBDS CONSTRUCTORS LLC DBA MK CONSTRUCTORSNovember 18, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Jefferson County is set to approve Change Order No. 2 with BDS Constructors, LLC d/b/a MK Constructors for the Crane Bayou Pump Station Generators and Building project, adding $41,347 to the contract and extending the schedule by 20 days. The amendment brings the total contract value to $1,590,347 under the CDBG-DR-funded project.

Contract Details

Contract Amount

$41,347.00 (change order); new total $1,590,347.00

Vendor

BDS CONSTRUCTORS LLC DBA MK CONSTRUCTORS

Agency

Jefferson County, TX

Contract Type

CONSTRUCTION

Document Date

November 18, 2025

Contract Term

Additional twenty (20) contract days, total 610 calendar days

Renewal Info

Second change order to IFB 23-035/JW; extends total contract time to 610 calendar days and increases total compensation to $1,590,347.00.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free