Change Order Approved For Crane Bayou Pump Station Project
Trusted by teams at
Description
Jefferson County is set to approve Change Order No. 2 with BDS Constructors, LLC d/b/a MK Constructors for the Crane Bayou Pump Station Generators and Building project, adding $41,347 to the contract and extending the schedule by 20 days. The amendment brings the total contract value to $1,590,347 under the CDBG-DR-funded project.
Contract Details
Contract Amount
$41,347.00 (change order); new total $1,590,347.00
Vendor
BDS CONSTRUCTORS LLC DBA MK CONSTRUCTORS
Agency
Jefferson County, TX
Contract Type
CONSTRUCTION
Document Date
November 18, 2025
Contract Term
Additional twenty (20) contract days, total 610 calendar days
Renewal Info
Second change order to IFB 23-035/JW; extends total contract time to 610 calendar days and increases total compensation to $1,590,347.00.
More from BDS CONSTRUCTORS LLC DBA MK CONSTRUCTORS
More from Jefferson County
Jefferson County Commissioners Court Agenda May 12, 2026
Jefferson County Commissioners Court Agenda May 12, 2026
Jefferson County Commissioners Court Agenda May 12, 2026
Jefferson County Commissioners Court Agenda May 12, 2026
Jefferson County Commissioners Court Agenda May 12, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.