CONSTRUCTIONRECOMMENDED

Pavement Improvement Contract Recommended To Ford Asphalt

District administration recommends awarding Ford Asphalt a pavement and track surface construction contract for Independence Elementary, Westwood Trail Academy, and Barnwell Middle School. The proposed award totals $849,000 in base and alternate work plus a 5% contingency, for $891,450 in hard costs, with work scheduled between the 2025–26 and 2026–27 school years.

Status
RECOMMENDED
Document date
May 21, 2026
Contract type
CONSTRUCTION
Vendor
Ford Asphalt
Agency
Francis Howell R-III School District · MO

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$800,000 base bid plus $22,000 Alternate 2, $12,000 Alternate 3, and $15,000 Alternate 4, total $849,000; plus 5% contingency $42,450, total project hard cost $891,450
Contract type
CONSTRUCTION
Contract term
Construction to begin at conclusion of 2025–26 academic year and be completed prior to start of 2026–27 academic year
Renewal
One-time construction project with a defined completion window between academic years; no renewal terms are described.
Document type
StaffReport
Source document
Board of Education Staff Report Purchase for Prior Approval Independence, Westwood, Barnwell Pavement Improvements 2026-05-21

Related contracts

Other contracts from Ford Asphalt.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Francis Howell R-III School District?

Ford Asphalt was awarded this construction contract by Francis Howell R-III School District, as recorded on May 21, 2026. The contract value is $800,000 base bid plus $22,000 Alternate 2, $12,000 Alternate 3, and $15,000 Alternate 4, total $849,000; plus 5% contingency $42,450, total project hard cost $891,450.

How much is the Ford Asphalt contract with Francis Howell R-III School District worth?

The Ford Asphalt contract with Francis Howell R-III School District is valued at $800,000 base bid plus $22,000 Alternate 2, $12,000 Alternate 3, and $15,000 Alternate 4, total $849,000; plus 5% contingency $42,450, total project hard cost $891,450, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in Board of Education Staff Report Purchase for Prior Approval Independence, Westwood, Barnwell Pavement Improvements 2026-05-21 (StaffReport), dated May 21, 2026 from Francis Howell R-III School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Ford Asphalt hold?

Ford Asphalt may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Ford Asphalt's profile

What is Francis Howell R-III School District currently buying?

Explore Francis Howell R-III School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Francis Howell R-III School District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free