Council Approves $912k Park Project Change Order
Trusted by teams at
Description
On September 22, 2025, the Council approved FORMA Construction’s $912,683.85 change order to provide additional general conditions for the Park Bond projects.
Contract Details
Contract Amount
$912,683.85
Vendor
FORMA CONSTRUCTION
Agency
City of Shoreline, WA
Contract Type
CONSTRUCTION
Document Date
June 8, 2026
Contract Term
Approved September 22, 2025 (change order, specific duration not stated)
Renewal Info
Approved as a contract change order for scope/general conditions; does not alter overall contract renewal structure.
More from FORMA CONSTRUCTION
More from City of Shoreline
City of Shoreline AgendaPacket Proclamation of Juneteenth 2026-06-08
City of Shoreline Staff Report Authorize the City Manager to Execute Guaranteed Maximum Price Amendment 3.2 with FORMA Construction 2026-06-08
City of Shoreline Staff Report Authorize the City Manager to Execute Guaranteed Maximum Price Amendment 3.2 with FORMA Construction 2026-06-08
City of Shoreline Staff Report Authorize the City Manager to Execute Guaranteed Maximum Price Amendment 3.2 with FORMA Construction 2026-06-08
City of Shoreline Staff Report Authorize the City Manager to Execute Guaranteed Maximum Price Amendment 3.2 with FORMA Construction 2026-06-08
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.