CONSTRUCTIONAMENDED

Marion County School District Agenda School Board Meeting 2026-05-26

Osceola Middle Gym Schedule Extended for Added Canopy

$0.00 (time extension only)Marion County School DistrictWHARTON-SMITH INCMay 26, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Marion County School Board approved a no-cost change order with Wharton-Smith, Inc. for the Osceola Middle School gym project, extending completion into summer 2026 to add a bus ramp canopy within the existing GMP. Substantial completion is now due July 31, 2026.

Contract Details

Contract Amount

$0.00 (time extension only)

Vendor

WHARTON-SMITH INC

Agency

Marion County School District, FL

Contract Type

CONSTRUCTION

Document Date

May 26, 2026

Contract Term

Substantial completion extended to July 31, 2026; final completion to August 30, 2026

Renewal Date

2026-08-30

Renewal Info

Change order extends substantial completion to July 31, 2026 and final completion to August 30, 2026 without increasing the GMP.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free