Change Order Reduces Earle Asphalt Roadway Contract
Trusted by teams at
Description
Brick Township approved a $19,049.89 deduct change order with Earle Asphalt Company for roadway improvements on North Lake Drive, Olive Court and Vista Court, reducing the contract to $438,263.24 and authorizing final payment and bond release. The project work has been accepted as complete.
Contract Details
Contract Amount
-$19,049.89 change (new total $438,263.24)
Vendor
EARLE ASPHALT COMPANY
Agency
Township of Brick, NJ
Contract Type
CONSTRUCTION
Document Date
June 23, 2026
Renewal Info
Change Order #1 is a final adjustment reducing the contract amount and closing out the project.
More from EARLE ASPHALT COMPANY
More from Township of Brick
Brick Township Council AgendaPacket Caucus/Public Meeting 2026-06-23
Brick Township Council AgendaPacket Caucus/Public Meeting 2026-06-23
Brick Township Council AgendaPacket Caucus/Public Meeting 2026-06-23
Brick Township Council AgendaPacket Caucus/Public Meeting 2026-06-23
Brick Township Council AgendaPacket Caucus/Public Meeting 2026-06-23
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.