Township of Verona Resolution 2025-286 Change Order #1

Verona Extends Booster Station Contract Completion Date

No cost change orderTownship of VeronaSOVEREIGN CONSULTINGDecember 15, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Township of Verona approved Change Order #1 to Contract No. 2024-20 with Sovereign Consulting for the Claridge Drive Booster Pumping Station. The no-cost change order extends the project substantial completion date by 119 days to June 1, 2026 to accommodate long lead times for the prefabricated building and generator.

Contract Details

Contract Amount

No cost change order

Vendor

SOVEREIGN CONSULTING

Agency

Township of Verona, NJ

Contract Type

CONSTRUCTION

Document Date

December 15, 2025

Contract Term

Project substantial completion date extended to June 1, 2026 (additional 119 calendar days)

Renewal Date

2026-06-01

Renewal Info

Change Order #1 grants a no-cost time-only extension of 119 calendar days, revising the substantial completion date from February 2, 2025 to June 1, 2026. No changes to contract price are included in this amendment.