FM 51 Booster Pump Station Contract With Acadia

$2,807,662 (revised total $2,789,300 referenced in change order table appears for 537-060; this line’s revised total not clearly restated)WALNUT CREEK SUDACADIAApril 18, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Walnut Creek SUD’s 2023 Bond Project 537-063 engages Acadia to build a new Booster Pump Station on FM 51, awarded for $2,807,662 and amended via change order to add concrete pads for filter equipment. The project is 90% complete with $2,696,638 spent as of March 31, 2026.

Contract Details

Contract Amount

$2,807,662 (revised total $2,789,300 referenced in change order table appears for 537-060; this line’s revised total not clearly restated)

Vendor

ACADIA

Agency

WALNUT CREEK SUD, TX

Contract Type

CONSTRUCTION

Document Date

April 18, 2026

Renewal Info

Change Order #1 added construction of concrete pads for filter equipment mounting; revised total contract amount confirmed at $2,807,662 in the change order schedule.