Final Payment and Change Order for Water Project Approved
Trusted by teams at
Description
Atwood City Council approved final pay application and a deductive change order for BSB Construction on Water Project #244-C1-008. The council authorized a final payment of $62,977.60 and certified project completion, with total project cost set at $501,072.45 after a $62,762.55 decrease.
Contract Details
Contract Amount
$62,977.60 (final payment), total project $501,072.45, -$62,762.55 change order
Vendor
BSB CONSTRUCTION
Agency
City of Atwood, KS
Contract Type
CONSTRUCTION
Document Date
September 18, 2025
Renewal Date
2025-09-18
Renewal Info
Contract amended by change order #2 reducing project cost. No further renewal or extension stated.