Henry Point Working Waterfront Project Combined Committee Meeting Minutes 2026-04-16

Contractor Jim Carver advances pre-construction submittals

Town of JonesportCARVER, JIMApril 16, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Contractor Jim Carver continues pre-construction activities for the Henry Point Working Waterfront Project, including material and system submittals for review and approval. These submittals cover erosion control, geotextiles, storm drainage, and electrical systems.

Contract Details

Vendor

CARVER, JIM

Agency

Town of Jonesport, ME

Contract Type

CONSTRUCTION

Document Date

April 16, 2026